Difference between revisions of "Costing Error Message"
Asp-luqman (talk | contribs) (→Error Message Log) |
|||
(13 intermediate revisions by 3 users not shown) | |||
Line 4: | Line 4: | ||
Daftar semua error yang akan mungkin akan tampil pada saat proses Calculate Costing dan cara menyelesaikannya. | Daftar semua error yang akan mungkin akan tampil pada saat proses Calculate Costing dan cara menyelesaikannya. | ||
+ | <br> | ||
+ | Pada dasar proses Costing dilakukan oleh background process namun dengan dibuatnya fitur baru Costing By Product dimana terdapat button di window product untuk menjalankan Calculate Cost per product sehingga end user dapat langsung melakukan troubleshooting atau perbaikan secara cepat. | ||
+ | |||
+ | Costing Error Log juga ditampilan secara massal untuk semua product di window [[Costing Error Log|Costing Error Log]] selain di tampilkan untuk masing-masing pada window [[Product|Product]]. | ||
=== Error Message Log === | === Error Message Log === | ||
Line 10: | Line 14: | ||
! Transaction Type !! Process !! Possible Error !! How to solve | ! Transaction Type !! Process !! Possible Error !! How to solve | ||
|- | |- | ||
− | | Shipment, <br>Receipt Return, <br>Receipt Negative, <br>Inventory Decrease, <br>InventoryClosing, <br>Internal Movement From, <br>Internal Consumption || Cost is getting by search average costing record of the product with costing start date is smaller or same with transaction process date, and costing end date is larger than transaction process date. | + | | '''Shipment, <br>Receipt Return, <br>Receipt Negative, <br>Inventory Decrease, <br>InventoryClosing, <br>Internal Movement From, <br>Internal Consumption''' || Cost is getting by search average costing record of the product with costing start date is smaller or same with transaction process date, and costing end date is larger than transaction process date. |
Sample query :<br> | Sample query :<br> | ||
CostingDateFrom <= TransactionProcessDate<br> | CostingDateFrom <= TransactionProcessDate<br> | ||
Line 16: | Line 20: | ||
CostingType = ‘AVA’<br> | CostingType = ‘AVA’<br> | ||
CostingCost != null<br> | CostingCost != null<br> | ||
− | || @NoAverageCostDefined@ || @NoAverageCostDefined@ = create costing record on tab costing with setup like on the sample Query | + | || @NoAverageCostDefined@ || @NoAverageCostDefined@ = create costing record on tab costing with setup like on the sample Query Tambah warehouse sesui dengan warehouse transaksi yang error |
|- | |- | ||
− | | ShipmentReturn || Method to calculate cost of Returned Shipments. Cost is calculated based on the cost of the original receipt. <br>When no receipt is found the default cost is returned (Purchase Price List of the product)|| @NoPriceListOrStandardCostForProduct@ || @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner. | + | | '''ShipmentReturn''' || Method to calculate cost of Returned Shipments. Cost is calculated based on the cost of the original receipt. <br>When no receipt is found the default cost is returned (Purchase Price List of the product)|| @NoPriceListOrStandardCostForProduct@ || @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner. |
|- | |- | ||
− | | ShipmentVoid || Cost is get from transaction of canceled Shipment line on the date it is canceled. || @NoCanceledLineFoundForTrx@ || @NoCanceledLineFoundForTrx@ = canceled line should be auto generate when change document status to void. | + | | '''ShipmentVoid''' || Cost is get from transaction of canceled Shipment line on the date it is canceled. || @NoCanceledLineFoundForTrx@ || @NoCanceledLineFoundForTrx@ = canceled line should be auto generate when change document status to void. |
|- | |- | ||
− | | ShipmentNegative, <br>InternalConsNegative|| Calculates the cost of a negative Shipment line. By default if the product is purchased the cost is based on its Purchase Price List.|| @NoPriceListOrStandardCostForProduct@ || @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). <br>If the transaction have business partner, it might get purchase price list from business partner. | + | | '''ShipmentNegative''', <br>'''InternalConsNegative'''|| Calculates the cost of a negative Shipment line. By default if the product is purchased the cost is based on its Purchase Price List.|| @NoPriceListOrStandardCostForProduct@ || @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). <br>If the transaction have business partner, it might get purchase price list from business partner. |
|- | |- | ||
− | | | + | | '''InternalConsVoid''' || Cost is get from original transction of internal consumption. The cost flow is on InternalCons part.|| n/a || n/a |
|- | |- | ||
− | | | + | | '''Receipt''' || calculates the cost of a Receipt line based on its related order price. When no order is found, the cost based on the newer of the following three values is returned: <br>1. Last purchase order price of the receipt's vendor for the product, <br>2. Purchase pricelist of Business Partner.|| @NoPriceListOrStandardCostForProduct@ || @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date).<br> If the transaction have business partner, it might get purchase price list from business partner. |
|- | |- | ||
− | | | + | | '''ReceiptVoid''' || get the cost from transaction of canceled Shipment line on the date it is canceled. || NoCanceledLineFoundForTrx || @NoCanceledLineFoundForTrx@ = canceled line should be auto generate when change document status to void. |
|- | |- | ||
− | | | + | | '''InventoryIncrease, <br>InventoryOpening''' || • Cost is get by Calculates the total cost amount of a physical inventory(column cost on table M_InventoryLine) and multiply it with Movement Quantity. |
+ | When there is no cost on M_ InventoryLine Default Cost is used (Purchase Price List of the product). | ||
+ | || @NoPriceListOrStandardCostForProduct@ || @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner.ple | ||
|- | |- | ||
− | | | + | | '''IntMovementTo''' || • Calculates the total cost amount of an incoming internal movement. The cost amount is the same than the related outgoing transaction(Movement From). The outgoing transaction(Movement From) cost is calculated if it has not been yet. || NoInternalMovementTransactionFound || @NoInternalMovementTransactionFound@ = this should cannot be happen, because the transaction is always come in pair. Example : Movement From and Movement To Transaction. |
|- | |- | ||
− | | | + | | '''BomPart''' (Production Plan, product that consumed as part to make a product) || • First the process is calculate other pending WIP BOM Transaction, after done calculate pending cost, Cost is getting by search average costing record of the product with costing start date is smaller or same with transaction process date, and costing end date is larger than transaction process date. |
+ | <br>Sample query : | ||
+ | <br>CostingDateFrom <= TransactionProcessDate | ||
+ | <br>CostingDateTo > TransactionProcessDate | ||
+ | <br>CostingType = ‘AVA’ | ||
+ | <br>CostingCost != null | ||
+ | || @NoAverageCostDefined@ || @NoAverageCostDefined@ = create costing record on tab costing with setup like on the sample Query. | ||
|- | |- | ||
− | | | + | | '''BomProduct''' (Production Plan, product that will be Produced) || Cost of BomProduct is getting by calculate all BomPart(-P) then sum all the cost of the part.|| n/a || n/a |
|- | |- | ||
− | | | + | | '''ManufacturingConsumed''' (Work Effort) || First the process run MA_PRODUCTION_COST function if the transaction productionLine is not calculated yet. Then cost is get from column Calccost on table M_ProductionLine that has been calculate when run the function before. If Column Calccost is null then return 0 as cost. || n/a || n/a |
|- | |- | ||
− | | | + | | '''ManufacturingProduced''' (Work Effort) || • Same like ManufacturingConsumed, First the process run MA_PRODUCTION_COST function if the transaction productionLine is not calculated yet. <br>Then cost is get from column Calccost on table M_ProductionLine that has been calculate when run the function before. <br>If Column Calccost is null then return 0 as cost. |
+ | <br>Note : <br>The Different is, the cost is Multiply with Movement Quantity. | ||
+ | || n/a || n/a | ||
|- | |- | ||
| Example || Example || Example || Example | | Example || Example || Example || Example | ||
Line 46: | Line 60: | ||
| Example || Example || Example || Example | | Example || Example || Example || Example | ||
|} | |} | ||
+ | |||
+ | === Another Attention during TroubleShooting of Costing === | ||
+ | |||
+ | Perlu memastikan beberapa parameter berikut: | ||
+ | <br> | ||
+ | 1. Pada M Product Transaction is processed harus "No" | ||
+ | <br> | ||
+ | 2. Pada M Product Transaction costing status harus "NC" | ||
+ | <br> | ||
+ | 3. Costing Rule harus di set pada Organization yang sesuai | ||
+ | <br> | ||
+ | 4. Pada menu Preference, costing start date harus di set valuenya | ||
+ | <br> | ||
+ | 5. Product Type Harus "I" | ||
+ | <br> | ||
+ | 6. Product Harust Stocked | ||
+ | |||
Latest revision as of 11:42, 7 December 2022
Back to Troubleshooting |
Introduction
Daftar semua error yang akan mungkin akan tampil pada saat proses Calculate Costing dan cara menyelesaikannya.
Pada dasar proses Costing dilakukan oleh background process namun dengan dibuatnya fitur baru Costing By Product dimana terdapat button di window product untuk menjalankan Calculate Cost per product sehingga end user dapat langsung melakukan troubleshooting atau perbaikan secara cepat.
Costing Error Log juga ditampilan secara massal untuk semua product di window Costing Error Log selain di tampilkan untuk masing-masing pada window Product.
Error Message Log
Transaction Type | Process | Possible Error | How to solve |
---|---|---|---|
Shipment, Receipt Return, Receipt Negative, Inventory Decrease, InventoryClosing, Internal Movement From, Internal Consumption |
Cost is getting by search average costing record of the product with costing start date is smaller or same with transaction process date, and costing end date is larger than transaction process date.
Sample query : |
@NoAverageCostDefined@ | @NoAverageCostDefined@ = create costing record on tab costing with setup like on the sample Query Tambah warehouse sesui dengan warehouse transaksi yang error |
ShipmentReturn | Method to calculate cost of Returned Shipments. Cost is calculated based on the cost of the original receipt. When no receipt is found the default cost is returned (Purchase Price List of the product) |
@NoPriceListOrStandardCostForProduct@ | @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner. |
ShipmentVoid | Cost is get from transaction of canceled Shipment line on the date it is canceled. | @NoCanceledLineFoundForTrx@ | @NoCanceledLineFoundForTrx@ = canceled line should be auto generate when change document status to void. |
ShipmentNegative, InternalConsNegative |
Calculates the cost of a negative Shipment line. By default if the product is purchased the cost is based on its Purchase Price List. | @NoPriceListOrStandardCostForProduct@ | @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner. |
InternalConsVoid | Cost is get from original transction of internal consumption. The cost flow is on InternalCons part. | n/a | n/a |
Receipt | calculates the cost of a Receipt line based on its related order price. When no order is found, the cost based on the newer of the following three values is returned: 1. Last purchase order price of the receipt's vendor for the product, 2. Purchase pricelist of Business Partner. |
@NoPriceListOrStandardCostForProduct@ | @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner. |
ReceiptVoid | get the cost from transaction of canceled Shipment line on the date it is canceled. | NoCanceledLineFoundForTrx | @NoCanceledLineFoundForTrx@ = canceled line should be auto generate when change document status to void. |
InventoryIncrease, InventoryOpening |
• Cost is get by Calculates the total cost amount of a physical inventory(column cost on table M_InventoryLine) and multiply it with Movement Quantity.
When there is no cost on M_ InventoryLine Default Cost is used (Purchase Price List of the product). |
@NoPriceListOrStandardCostForProduct@ | @NoPriceListOrStandardCostForProduct@ = Because the transaction costing is average there is no way to create standard cost, the way to solve it is to create valid Purchase Price List (if the error still occur please check price list valid date and compare to transaction date). If the transaction have business partner, it might get purchase price list from business partner.ple |
IntMovementTo | • Calculates the total cost amount of an incoming internal movement. The cost amount is the same than the related outgoing transaction(Movement From). The outgoing transaction(Movement From) cost is calculated if it has not been yet. | NoInternalMovementTransactionFound | @NoInternalMovementTransactionFound@ = this should cannot be happen, because the transaction is always come in pair. Example : Movement From and Movement To Transaction. |
BomPart (Production Plan, product that consumed as part to make a product) | • First the process is calculate other pending WIP BOM Transaction, after done calculate pending cost, Cost is getting by search average costing record of the product with costing start date is smaller or same with transaction process date, and costing end date is larger than transaction process date.
|
@NoAverageCostDefined@ | @NoAverageCostDefined@ = create costing record on tab costing with setup like on the sample Query. |
BomProduct (Production Plan, product that will be Produced) | Cost of BomProduct is getting by calculate all BomPart(-P) then sum all the cost of the part. | n/a | n/a |
ManufacturingConsumed (Work Effort) | First the process run MA_PRODUCTION_COST function if the transaction productionLine is not calculated yet. Then cost is get from column Calccost on table M_ProductionLine that has been calculate when run the function before. If Column Calccost is null then return 0 as cost. | n/a | n/a |
ManufacturingProduced (Work Effort) | • Same like ManufacturingConsumed, First the process run MA_PRODUCTION_COST function if the transaction productionLine is not calculated yet. Then cost is get from column Calccost on table M_ProductionLine that has been calculate when run the function before. If Column Calccost is null then return 0 as cost.
|
n/a | n/a |
Example | Example | Example | Example |
Example | Example | Example | Example |
Another Attention during TroubleShooting of Costing
Perlu memastikan beberapa parameter berikut:
1. Pada M Product Transaction is processed harus "No"
2. Pada M Product Transaction costing status harus "NC"
3. Costing Rule harus di set pada Organization yang sesuai
4. Pada menu Preference, costing start date harus di set valuenya
5. Product Type Harus "I"
6. Product Harust Stocked